The Mythical Man-Month
Assigning more programmers to a project running behind schedule will make it even later, due to the time required for the new programmers to learn about the project, as well as the increased communication overhead. When N people have to communicate among themselves (without a hierarchy), as N increases, their output M decreases and can even become negative (i.e. the total work remaining at the end of a day is greater than the total work that had been remaining at the beginning of that day, such as when many bugs are created).
* Group Intercommunication Formula: n(n − 1) / 2
* Example: 50 developers -> 50(50 − 1) / 2 = 1225 channels of communication
wikipedia (et c'est correct)
99% des étudiants n'ont pas compris l'an dernier ce que veut dire homme-mois et que 10 hommes pendant un mois est = à 1 homme pendant 1 mois, comme un carré de 5 x 2 a la même surface qu'un carré de 10 x 2 m. J'ai répété. En vain ! bof évident ! on sait ! ce ne sont que des maths de maternelle !
Et le pb est que 9 femmes ne font pas 9 bébés en 1 mois ! L'H-M c'est bien pratique ...pour facturer ! mais pour planifier, non. A moins qu'il s'agisse de tâches qui ne demandent pas de coordination.
Présidentielle 2027 : entre poussée populiste et désir de bascule
politique, les ambiguïtés de la demande de rupture chez les Français
-
La France semble de plus en plus imprégnée de sentiments qui la
prédisposent à une bascule populiste, mais elle n’est pas non plus
inéluctable, analyse Bri...
Il y a 4 jours


Aucun commentaire:
Enregistrer un commentaire